Projects Funded
Project Name: Central House
Project Sponsor: Rivavect Investments (Pty) Ltd
The Central House project is located in the heart of the Roodepoort CBD at the corner of Van Wyk and Joubert Street. The project will entail the purchase and conversion of the Central House. The project will yield 2 bachelor, 107 one-bed and 11 two-bed units.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Central House |
2011/12 |
R25 260 983 |
R5 000 000 |
R20 260 983 |
Project Name: Italic Mansions
Project sponsor: Shamzang Property Investment Holdings (Pty) Ltd
The Italic Mansions project is located on 36 Plein Street in the Johannesburg CBD. The projects involve the acquisition and converting of 123 communal rooms into 64 self contained one bedroom flats.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Italic Mansion |
2011/12 |
R19 491 900 |
R5 847 570 |
R13 644 330 |
Project Name: Kgorong Estate
Project sponsor: BM Molefi Properties 241 (Pty) Ltd
The Kgorong estate project is situated in Protea Glen, Ext. 1, Soweto. The project entails the development of a residential apartment block with of 282 units. The development will consist of 47 double storey blocks with 6 units per block; it will also have laundry rooms, braai areas, car wash areas and a guard house.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Kgorong Estate |
2011/12 |
R72 725 000 |
R21 817 500 |
R50 907 500 |
Project Name: Fleurhof
Project Sponsor: Madulamoho Housing Association (MHA)
The project is a new development located in Fleurhof Ext 2 and consists of:
- 10540 unit area plus
- 3693 stairs and landing
- 68 offices
- 132 drying yard
- 130 refuse yard
Total 14301m2 (excl drying and drying yard)
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Fleurhof Views |
2011 |
R77 817 926
(Incl. Land) |
R23 345 378 |
R54 472 548 |
Project Name: The Ridge Hotel
Project sponsor: Tenitor Properties
The Ridge Hotel is located on Erven 185,187,189,191 and 1411 in Berea. The project entailed the acquisition and refurbishment of rooms into affordable housing units. The Ridge Hotel has four properties: the 14 storey main hotel building, the 4 storey hotel extension, a two storey (Helen Suzman) building and Kwa Ngombe, a 3 storey standalone building. These properties could yield 12 rooftops, 210 bachelor units and 12 one-bedroom units.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| The Ridge Hotel |
2011 |
R37 873 000 |
R11 361 900 |
R26 511 100 |
Project Name: Lubraco House
Project sponsor: Lionshare New Properties 1 CC
Lubraco House which is situated on Erf 532 and Erf 533 is a seven storey building with a basement. The project was a conversion of 7 storeys of office space to residential development to create 63 units; of 57x bachelor units (average 35 sq. metres) and 6x 1-bedroom units. The building also has 2 shops on the ground floor and a storage basement used by the shops.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Lubraco House |
2010 |
R13 433 154 |
R3 700 000 |
R9 733 154 |
Project Name: Tau Village
Project sponsor: Yeast City Housing (YCH)
The Tau Village project is located on 279 Struben Street, Pretoria. The project entailed reconstruction and refurbishment from a hotel to a mixed use facility of 109 two storey walk-up housing units. This also includes accommodation for aged and communal accommodation for girls at risk and upgraded commercial space on the ground floor. In addition the project has a drop in centre and a baby care centre.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Tau Village |
2009 |
R30 000 000 |
R9 000 000 |
R21 000 000 |
Project Name: Allenby
Project sponsor: Madulamoho Housing Association (MHA)
The Allenby project is located on 45 Claim Street, Hillbrow. The project entailed refurbishment of quality communal units. They have installed a fingerprint identification system with turnstile gate to further improve the security of the building. The total number of units is 109.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Allenby |
2009 |
R10 900 000 |
R3 270 000 |
R7 630 000 |
Project Name: Hlanganani
Project Sponsor: Johannesburg Housing Company (JHC)
The Hlanganani project is located to the north-west of the Johannesburg's city in the first of government's mega integrated housing project – Cosmo City. The Hlanganani project consists of 281 units in 21 blocks of two and three storey walk up townhouse type units with open parking bays. The entire development is fenced with a central security controlled entrance for vehicles and pedestrians. The Hlanganani project has a mix of one-bedroom, two-bedroom and three-bedroom units.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Hlanganani |
2008 |
R85 000 000 |
R20 000 000 |
R65 000 000 |
Project Name: Montrose Mansions
Project Sponsor: Maseleng Investments (Pty) Ltd
The Montrose Mansions project is located on the corner of Von Wielligh and Jeppe Street in the Johannesburg CBD. The project entailed the acquisition and conversion of commercial office space to rental housing units. The project comprises of a twelve story building that accommodates 10 floors to 120 one bedroom units with 1st floor office and ground floor retail shops totalling 1382m2..
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Montrose Mansions |
2008 |
R15 858 000 |
R3 100 000 |
R11 680 000 |
Project Name: Orlando Ekhaya
Project Sponsor: Johannesburg Social Housing Company (JOSHCO)
The Orlando Ekhaya project is located on Nicholas Road behind the Orlando Power Station cooling towers in Orland East, Soweto. The project entailed Phase 1 - Conversion of Hostel Block A into 102 family units consisting of 24 one-bedroom units and 78 two-bedroom units. Phase 2 - Construction of a new 3 Storey walk up complex. This comprises of 18 blocks of 6 two-bedroom units each, a total of 108 two-bedroom units. The refurbishment of Block B will consist of 61 two-bedroom units. The total number of units is 266.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Pennyville |
2007 |
R64 682 146 |
R12 888 948 |
R51 793 198 |
Project Name: Pennyville
Project Sponsor: Johannesburg Social Housing Company (JOSHCO)
The project is situated opposite the New Canada station and adjacent to New Canada Road. The project borders the Noordgesig Township. The project has easy access to Johannesburg's City Centre via Main Reef Road.
The project is a three storey walk-up development consisting of 9 blocks of housing units. Each block consists of +- 40 two-bedroom units with court yards in the middle which serve as a common area for community activities, washing lines and the children's play area. The total number of housing units is 200.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Pennyville |
2007 |
R40 318 553 |
R8 063 710 |
R32 254 843 |
Project Name: Roodepoort
Project Sponsor: Johannesburg Social Housing Company (JOSHCO)
The Roodepoort project is located within the Roodepoort CBD adjacent to the taxi rank and within walking distance to the retail sector in the CBD. The Roodepoort project consists of 432 two storey walk-up units. The project has a mix of one-bedroom and two-bedroom type of units.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Roodepoort |
2007 |
R98 316 596 |
R19 663 319 |
R78 653 277 |
Project Name: Phase 2B
Project sponsor: Greater Germiston Inner City Housing Company (GGICHC)
The project is located on stand 808 Germiston and stand 948 Delville in the Ekurhuleni metropolitan. The project comprises of 286 rental units with an average unit size of 44m2.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Phase 2B |
2006 |
R7 500 000 |
N/A |
N/A |
Project Name: Pharoe Park
Project sponsor: Greater Germiston Inner City Housing Company (GGICH)
This project is located on the outskirts of the Germiston, CBD. The project consist of 9 bachelor, 142 one bedroom, 221 two bedroom and 65 three bedroom units. The total number of unit is 437.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Pharoe Park |
2006 |
R7 500 000 |
N/A |
N/A |
Project Name: Manners Mansion
Project Sponsor: Jozi Housing
The Manners Mansion is located on the corner of Pritchard and Sauer Street in the CBD. The project entailed the acquisition and refurbishment of Manners Mansion Building. The building comprises of a 13 storey building and has a combination of 80 residential units averaging 60m2 and 9 retail tenants at the ground floor.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Manners Mansion |
2006 |
R14 182 334 |
R2 836 466 |
R11 345 868 |
Project Name: Kliptown
Project sponsor: GDoH
The Kliptown project is located in Kliptown, Soweto. The project was split into two phases: the Walter Sisulu Square project delivering 478 units and the Golf Course project delivering 932 units.
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Kliptown |
2005 |
R190 390 403 |
R34 000 000 |
R156 390 403 |
Project Name: Brickfields
Project sponsor: Johannesburg Housing Company (JHC)
The project is located between West and Bezuidenhout Street at the foot of the Nelson Mandela Bridge in the Johannesburg CBD. This project was done in two phases the 1st phase comprised of 631 units and the 2nd phase comprised of 178 units. The project comprises of a mixed use of 809 units. The project consists of low to moderate rise buildings, most being three storey walk-ups
| Project |
Project Construction year |
Total Development cost excl. land (incl. VAT) |
GPF Funding |
Co-sponsor Funding |
| Brickfields |
2004 |
R120 300 000 |
R24 300 000 |
R106 000 000 |